Construction
(1) Construction of the clean operating department shall be carried out after the civil engineering work is completed and the site has been cleaned.
(2) Construction of clean operating rooms shall follow a defined sequence of procedures; dust-generating operations during system installation shall be avoided, and when installing HEPA filters or air supply terminals, dust-generating operations must be avoided.
(3) The construction procedure for clean operating rooms is shown in Figure 12.1 (other auxiliary rooms may refer to this procedure).
Completion of the main structure, positioning of exterior doors and windows → Re-checking reserved openings / Checking embedded pipelines → Dividing spatial zones and coordinating cross-trade operations → Floor waterproofing, cushion layer in place, leveling → Positioning of large equipment / Pipelines of various trades constructed in sequence according to coordinated elevations and spatial positions →
Inspection of pipelines, cleaning, pressure testing, leak detection, insulation → Repairing and sealing openings → Cleaning before concealment, concealed work acceptance, sealing and covering → Construction of the envelope structure, reserving installation positions for equipment such as instrument cabinets / Positioning of interior doors and windows → Cleaning of interstitial chases → Positioning and installation of suspended equipment bases and hangers →
Ceiling → Lighting installation → Completion of ceiling, walls and floors → Joint sealing → Indoor cleaning → Installation of indoor equipment and furnishings → Thorough cleaning → Equipment trial run, air blowing →
Indoor cleaning and air purge → Installation of terminal HEPA filters and accessories → Sealing of air supply outlets → Indoor sanitation treatment → System coordination → Opening air supply outlets for adjustment and testing → Completion acceptance → Comprehensive evaluation → Handover for use
Figure 12.1 Construction procedure for clean operating rooms
(4) The following records must be kept at all times during construction and installation.
- Records of concealed civil engineering work.
- Records of concealed pipeline work and system sealing.
- Records of equipment unpacking inspection.
- Records of pipeline pressure tests.
- Records of pure gas pipeline system purging.
- Records of air duct leakage checks.
- Records of air duct cleaning and sanitation.
- Records of individual equipment trial operation.
- Records of combined system trial operation.
- Intermediate acceptance sheets.
The record forms are shown in Tables 12.1 to 12.10.
Table 12.1 Record of Concealed Civil Works
Project Name and No.:
Name and No. of Divisional and Sub-divisional Works: Year Month Day
| Concealed Works Content | Cleaning Status | Attached Drawings and Notes | |||
|---|---|---|---|---|---|
| Divisional and Sub-divisional Name | Unit | Quantity | Method | Date | |
| Inspection Comments | |||||
| Foreman or Technical Supervisor: | Site Engineer: | ||||
| Client: (Official Seal) | Contractor: (Official Seal) | ||||
| Year Month Day | Year Month Day | ||||
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Table 12.2 Record of System Sealing for Concealed Pipeline Works
Project Name and No.:
Name and No. of Divisional and Sub-divisional Works: Year Month Day
Pipeline No.__Pipe Diameter__Material__Working Medium__
Inspection Prior to Concealment and Sealing__
Concealment and Sealing Method__
Sketch or Description:
| Inspection Comments | |
|---|---|
| Foreman or Technical Supervisor: | Site Engineer: |
| Client: (Official Seal) | Contractor: (Official Seal) |
| Year Month Day | Year Month Day |
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Table 12.3 Equipment Unpacking Inspection Record
Project Name and Number:
Sub-divisional Work Name and Number: Year Month Day
| Project Number | Equipment Name | ||
|---|---|---|---|
| Project Name | Construction Drawing No. |
Specification and Model________________________________
Manufacturer________________________________
Packaging Condition________________________________
____________________________________
Equipment Appearance Condition______________________________
____________________________________
Insulation Condition of the Electrical Part___________________________
____________________________________
Equipment Accessory Names (per Packing List)_________________________
____________________________________
Remarks________________________________
Foreman or Technical Director: Site Supervisor:
| Owner: (Official Seal) | Contractor: (Official Seal) |
|---|---|
| Year Month Day | Year Month Day |
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Table 12.4 Pipeline Pressure Test Record
Project Name and Number:
Name and Number of Divisional and Itemized Work: Year Month Day
| Divisional Work Name | Specification | Unit | Quantity | Test Pressure /Pa | Test Method | Duration /min | Pressure Drop /Pa | Conclusion |
|---|---|---|---|---|---|---|---|---|
| Remarks |
| Foreman or Technical Head: | Site Engineer: |
|---|---|
| Client: (Official Seal) | Contractor: (Official Seal) |
| Year Month Day | Year Month Day |
| Representative (Signature & Seal): | Representative (Signature & Seal): |
Table 12.5 Pipeline System Flushing (Degreasing) Record
Project Name and No.:
Name and No. of Divisional and Sub-divisional Work: Year Month Day
| Pipeline No. | Material | Working Medium | Flushing | Flushing | Flushing | Flushing | Flushing | Degreasing | Degreasing |
|---|---|---|---|---|---|---|---|---|---|
| Medium | Pressure | Flow Velocity | Number of Flushes | Appraisal | Medium | Appraisal | |||
| Inspection Comments |
Foreman or Technical Person in Charge: Construction Supervisor:
| Construction Unit: (Official Seal) | Construction Contractor: (Official Seal) |
|---|---|
| Year Month Day | Year Month Day |
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Table 12.6 Air Duct Leakage Inspection Record
Project Name and No.: Divisional and Itemized Work Name and No.:
System Name: Duct Name:
Inspection Method: Year Month Day
| Cleanliness Class | Duct Section | Duct Cross-section (Length × Width) /mm×mm | Leakage Point No. | Leaking Duct Location | Attached Drawings and Description |
|---|---|---|---|---|---|
| Inspection Comments | |||||
| Foreman or Technical Head: | Site Engineer: | ||||
| Client: (Seal) Year Month Day Representative (Signature): | Contractor: (Seal) Year Month Day Representative (Signature): |
Note: Duct name refers to the supply air duct or return air duct; duct section refers to the main duct, sub-main duct, or branch duct.
Table 12.7 Air Duct Cleaning Hygiene Record
Project Name and No.: Duct Name:
Name and No. of Sub-divisional and Itemized Work: Year Month Day
| Cleanliness Class | Duct Location | Duct Cross-section (Length×Width)/mm×mm | Cleaning Method | Cleaning Tools | Cleaning Medium | Attached Drawings and Notes |
|---|---|---|---|---|---|---|
| Inspection Comments | |
|---|---|
Foreman or Technical Director: Site Engineer:
| Client (Construction Unit): (Official Seal) | Contractor (Construction Unit): (Official Seal) |
|---|---|
| Year Month Day | Year Month Day |
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Note: Duct name refers to the supply air duct or return air duct; duct location refers to the main duct, sub-main duct, or branch duct.
Table 12.8 Equipment Single-Machine Trial Operation Record
Project Name and Number:
Divisional and Itemized Work Name and Number:
Equipment Name and Number:
Trial Operation Date: Year Month Day
| Trial Operation Content | |
|---|---|
| Trial Operation Result | |
| Evaluation Opinion |
| Construction Unit (Owner): (Official Seal) | Construction Contractor: (Official Seal) |
|---|---|
| Year Month Day | Year Month Day |
| Representative (Signature & Seal): | Representative (Signature & Seal): |
Table 12.9 System Joint Trial Operation Record
Project Name and No.:
Division and Sub-division Work Name and No.:
System Name and No.:
Trial Operation Date: Year Month Day
| Trial Operation Content | |
|---|---|
| Trial Operation Result | |
| Evaluation Opinion |
| Construction Unit (Owner): (Official Seal) | Construction Contractor: (Official Seal) |
|---|---|
| Year Month Day | Year Month Day |
| Representative (Signature/Seal): | Representative (Signature/Seal): |
Table 12.10 Intermediate Acceptance Form
Project Name and Number:
Name and Number of Divisional and Itemized Works:
Intermediate Acceptance Date: Year Month Day
| Work Content | |
|---|---|
| Intermediate Acceptance Result | |
| Outstanding Issues | |
| Evaluation Opinion | |
| Attachments | |
| Foreman or Technical Head: | Construction Supervisor: |
| Client: (Official Seal) | Contractor: (Official Seal) |
| Year Month Day | Year Month Day |
| Representative (Signature & Seal): | Representative (Signature & Seal): |